Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Marble — Calacatta, Entrance & Majlis Floors
Material Submittal
This page could not check who holds the decision on this item, so the decision panel is hidden. This is a setup problem, not a permissions one — public.can_approve() is unavailable.
Original submission
Contractor · Feb 16, 2026, 04:20 AMSlab photographs from the Carrara yard. Six-week lead time from order to site.
- Calacatta-Slab-Photographs.pdf2.8 KB
- Marble-Setting-Out-Layout.pdf2.7 KB
- ApprovedOwner · Feb 19, 2026, 01:05 PM
Slabs selected from the photographs. Order now — six weeks is already on the critical path.
Consultant · Feb 16, 2026, 01:20 PM
Before you approve: six weeks from order to site, and the majlis floor is on the critical path. If the selection moves again after this we lose the date.
Owner · Feb 16, 2026, 10:20 PM
Understood. This is the one I am sure about — place the order.