You are looking at a demonstration project.
Everything here is real inside Plars — the approvals, the money, the programme — but the people and the files are invented. You can read everything and change nothing. Start your own project.
Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Authorities & Permits
Track each authority permit — its status and documents.
- Dubai Municipality — Building Completion CertificateApproved
Raised by Contractor · 06 Jul 2026 · Lodged once Civil Defence cleared. Completion certificate is what practical completion hangs on.
No documents attached.
Status history (3)
- Approved10 Aug 2026 · Contractor
- Submitted06 Jul 2026 · Contractor
- Not started06 Jul 2026 · Contractor
- Dubai Civil Defence — Fire & Life SafetyApproved
Raised by Contractor · 09 Feb 2026 · Returned once: sprinkler coverage to the basement store was missing from the drawings. Resubmitted with the revised layout and cleared on 15 June.
- Consultant · 18 Aug 2026
Status history (5)
- Approved15 Jun 2026 · Contractor
- Submitted06 Apr 2026 · Contractor
- Rejected16 Mar 2026 · Contractor
- Submitted09 Feb 2026 · Contractor
- Not started09 Feb 2026 · Contractor
- DEWA — Electricity & Water ConnectionApproved
Raised by Contractor · 19 Jan 2026 · Permanent supply energised 6 April 2026. Temporary builder supply ran until then.
- Consultant · 18 Aug 2026
Status history (3)
- Approved06 Apr 2026 · Contractor
- Submitted19 Jan 2026 · Contractor
- Not started19 Jan 2026 · Contractor
- Dubai Municipality — Building PermitApproved
Raised by Contractor · 14 Jul 2025 · Issued before possession of site. Valid for the contract duration.
No documents attached.
Status history (3)
- Approved11 Aug 2025 · Contractor
- Not started14 Jul 2025 · Contractor
- Submitted14 Jul 2025 · Contractor