Villa — Nad Al Sheba

Guest (view only)

Plot 214, Nad Al Sheba 3, Dubai

This project is completed. It stays fully readable; an admin can reopen it from Handover.

RFIs

Formal requests for information, numbered and dated, answered by the consultant. Just need a quick answer from whoever knows? Ask a question instead. Each one dated, so how long it took is never in dispute.

1 question waiting for an answer 1 past the date it was needed. Longest waiting: 29 days.
  • RFI 4Overdue

    Warranty start date for the below-grade tanking

    Asked by Contractor on 11 Aug 2026 · needed by 16 Aug 2026 · waiting 29 days

    The applicator warranty is dated from application (November 2025), not from handover. Ten years from which date? The client is asking before signing.

    Waiting for the consultant to answer.

  • RFI 1Closed

    Slab thickness at the car porch

    Asked by Contractor on 14 Oct 2025 · needed by 20 Oct 2025 · answered after 2 days

    Structural drawing S-104 shows 200mm; the architectural section shows 250mm. Which governs?

    • Consultant · 10/16/2025

      250mm governs. S-104 is superseded — use the architectural section and confirm the rebar to suit.

  • RFI 2Closed

    Socket height in the majlis

    Asked by Contractor on 09 Mar 2026 · needed by 18 Mar 2026 · answered after 2 days

    Client asked for sockets at 300mm AFF rather than the 450mm on the drawing. Confirm?

    • Consultant · 3/11/2026

      300mm AFF confirmed throughout the majlis. Update the layout and issue Rev C.

  • RFI 3Closed

    MEP clash — containment against AHU ductwork, first floor lobby

    Asked by Contractor on 09 Apr 2026 · needed by 16 Apr 2026 · answered after 4 days

    Electrical containment at the first-floor lobby runs through the AHU duct at high level. Ceiling void is 350mm and both cannot pass. Which one drops?

    • Consultant · 4/14/2026

      Containment drops below the duct and the ceiling comes down 80mm across the lobby only. Coordinated section attached — the bulkhead is acceptable to the client.