Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Inspections
Ask for finished work to be looked at, and keep the answer.
- #7
MEP commissioning witness
PassedPlant room and all floors · ready Jul 14, 2026, 04:00 AM · asked by Contractor
AHUs, pumps and the distribution board ready for witnessed commissioning.
- PassedConsultant · Jul 14, 2026, 12:40 PM
Witnessed in full. Readings within tolerance; certificates to go in the O&M pack.
- #6
Pool shell — before tiling
CancelledRear garden · ready Apr 12, 2026, 04:00 AM · asked by Contractor
Shell and waterproofing ready for tiling.
- #5
North elevation blockwork — re-inspection
PassedNorth elevation, ground and first · ready Mar 19, 2026, 04:00 AM · asked by Contractor
Perpends filled and the movement joint made continuous at gridline 4. Ready for re-inspection.
- PassedConsultant · Mar 19, 2026, 08:00 AM
Rectification accepted. Cleared for plaster.
- #4
North elevation blockwork
FailedNorth elevation, ground and first · ready Mar 5, 2026, 04:00 AM · asked by Contractor
Blockwork complete to the north elevation, ready for plaster.
- FailedConsultant · Mar 5, 2026, 07:20 AM
Perpends unfilled over roughly 12 square metres at first floor level, and the movement joint at gridline 4 is not continuous. Rectify and re-request — do not plaster over this.
- #3
Roof slab reinforcement — before pour
PassedRoof slab, first floor · ready Jan 28, 2026, 03:00 AM · asked by Contractor
Slab reinforcement, service penetrations and edge shuttering complete.
- PassedConsultant · Jan 28, 2026, 06:00 AM
Correct against the drawing. Approved to pour.
- #2
Below-grade tanking — before backfill
Not attendedNorth and east retaining walls · ready Nov 10, 2025, 03:00 AM · asked by Contractor
Membrane and drainage board complete to both walls. Backfill booked for the 11th.
Nobody attended — work proceeded Nov 11, 2025, 04:15 AM
Nobody attended on the 10th or the morning of the 11th. Backfill could not be held any longer — photographs of every lap are in the Below-grade waterproofing set, taken before covering.
- #1
Raft reinforcement — before pour
PassedRaft, whole footprint · ready Nov 4, 2025, 03:00 AM · asked by Contractor
Bottom and top mats complete, cover blocks in, ready for the 5th.
- PassedConsultant · Nov 4, 2025, 05:30 AM
Spacing, cover and laps correct. Cleared to pour.