Inspections

Ask for finished work to be looked at, and keep the answer.

  • #7

    MEP commissioning witness

    Passed

    Plant room and all floors · ready Jul 14, 2026, 04:00 AM · asked by Contractor

    AHUs, pumps and the distribution board ready for witnessed commissioning.

    • PassedConsultant · Jul 14, 2026, 12:40 PM

      Witnessed in full. Readings within tolerance; certificates to go in the O&M pack.

  • #6

    Pool shell — before tiling

    Cancelled

    Rear garden · ready Apr 12, 2026, 04:00 AM · asked by Contractor

    Shell and waterproofing ready for tiling.

  • #5

    North elevation blockwork — re-inspection

    Passed

    North elevation, ground and first · ready Mar 19, 2026, 04:00 AM · asked by Contractor

    Perpends filled and the movement joint made continuous at gridline 4. Ready for re-inspection.

    • PassedConsultant · Mar 19, 2026, 08:00 AM

      Rectification accepted. Cleared for plaster.

  • #4

    North elevation blockwork

    Failed

    North elevation, ground and first · ready Mar 5, 2026, 04:00 AM · asked by Contractor

    Blockwork complete to the north elevation, ready for plaster.

    • FailedConsultant · Mar 5, 2026, 07:20 AM

      Perpends unfilled over roughly 12 square metres at first floor level, and the movement joint at gridline 4 is not continuous. Rectify and re-request — do not plaster over this.

  • #3

    Roof slab reinforcement — before pour

    Passed

    Roof slab, first floor · ready Jan 28, 2026, 03:00 AM · asked by Contractor

    Slab reinforcement, service penetrations and edge shuttering complete.

    • PassedConsultant · Jan 28, 2026, 06:00 AM

      Correct against the drawing. Approved to pour.

  • #2

    Below-grade tanking — before backfill

    Not attended

    North and east retaining walls · ready Nov 10, 2025, 03:00 AM · asked by Contractor

    Membrane and drainage board complete to both walls. Backfill booked for the 11th.

    Nobody attended — work proceeded Nov 11, 2025, 04:15 AM

    Nobody attended on the 10th or the morning of the 11th. Backfill could not be held any longer — photographs of every lap are in the Below-grade waterproofing set, taken before covering.

  • #1

    Raft reinforcement — before pour

    Passed

    Raft, whole footprint · ready Nov 4, 2025, 03:00 AM · asked by Contractor

    Bottom and top mats complete, cover blocks in, ready for the 5th.

    • PassedConsultant · Nov 4, 2025, 05:30 AM

      Spacing, cover and laps correct. Cleared to pour.