Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Invoice tracking
- Original budget
- AED 3,200,000.00
- Approved variations
- +AED 117,500.00
- Contract value
- AED 3,317,500.00
- Invoiced
- AED 3,317,500.00
- Paid
- AED 3,154,562.50
- Remaining
- AED 162,937.50
95% of the contract value paid.
Contract value is the original budget plus every approved variation, at its latest revision. Variations still pending are not counted.
Remaining counts money actually paid. Invoices raised but not yet paid are not deducted.
Main contract value as signed, 4 August 2025.
4 approved variations— what makes up the AED 117,500.00 addition
| Approved | Variation | Amount |
|---|---|---|
| Apr 15, 2026 | Lighting — Smart Control to Majlis, Living and External | +AED 45,000.00 |
| Apr 9, 2026 | Landscape — Omit Rear Pergola and Decking | −AED 38,000.00 |
| Mar 5, 2026 | Kitchen — Upgrade to Quartz Worktop | +AED 46,500.00 |
| Nov 3, 2025 | Basement — Additional Tanking to Retaining Wall | +AED 64,000.00 |
Advance payment
- Advance paid
- AED 150,000.00
- Recovered (20% of certificates)
- AED 150,000.00
- Still to recover
- AED 0.00
Paid before work started, so it is not payment for work done. It is recovered from each certificate until it is repaid, and recovery stops there — it can never take back more than was paid forward.
Fully recovered. Later certificates are no longer reduced.
Retention
- Held so far (10% of certificates)
- AED 165,875.00
- Released
- AED 82,937.50
- Still held
- AED 82,937.50
Retention is deducted from each certified amount and handed back in stages. It is money still owed, so it is included in Remaining above — not subtracted from it.
| Stage | Released on | Note | Amount | Recorded by |
|---|---|---|---|---|
| 14 Aug 2026 | First half released on practical completion, certified 10 August 2026. Balance falls due at the end of the defects liability period, 17 August 2027. | AED 82,937.50 | Owner |
Invoices
| Date | Reference | For | Claimed | Certified | Payable | Status | Recorded by | |
|---|---|---|---|---|---|---|---|---|
| 12 Aug 2026 | INV-006 | Final account: retention balance, approved variations and the pergola omission. | AED 347,500.00 | AED 347,500.00 | AED 347,500.00 | Paid | Contractor | |
| 30 Jun 2026 | INV-005 | Joinery, marble, MEP second fix and commissioning. | AED 560,000.00 | AED 560,000.00 | AED 560,000.00 | Paid | Contractor | |
| 28 Apr 2026 | INV-004 | MEP first fix, blockwork and internal plaster. | AED 590,000.00 | AED 590,000.00 | AED 590,000.00 | Paid | Contractor | |
| 10 Feb 2026 | INV-003 | Superstructure to roof slab, columns and staircase. | AED 720,000.00 | AED 640,000.00−AED 80,000.00 | AED 584,125.00 | AED 135,875.00 left | Contractor | |
| 12 Nov 2025 | INV-002 | Raft foundation and substructure blockwork. | AED 620,000.00 | AED 620,000.00 | AED 504,000.00 | AED 116,000.00 left | Contractor | |
| 05 Sep 2025 | INV-001 | Mobilisation, excavation and shoring. | AED 480,000.00 | AED 480,000.00 | AED 336,000.00 | AED 144,000.00 left | Contractor |
Payments
| Date paid | Against | Method | Note | Amount | Recorded by | |
|---|---|---|---|---|---|---|
| 16 Aug 2026 | INV-006 | Bank transfer | Final account settled on handover. | AED 347,500.00 | Owner | |
| 14 Aug 2026 | Not against an invoice | Bank transfer | First half of retention released at practical completion. | AED 82,937.50 | Owner | |
| 20 Jul 2026 | INV-005 | Bank transfer | Certificate 5: joinery, marble and commissioning. | AED 560,000.00 | Owner | |
| 18 May 2026 | INV-004 | Bank transfer | Certificate 4: no retention deducted — the cap was reached on the previous certificate. | AED 590,000.00 | Owner | |
| 28 Feb 2026 | INV-003 | Bank transfer | Certificate 3: 640,000 certified against 720,000 claimed — the 80,000 difference is the north-elevation rectification, which the contractor carries. Retention reached its 5% cap here. | AED 584,125.00 | Owner | |
| 01 Dec 2025 | INV-002 | Bank transfer | Certificate 2: 620,000 certified, less retention. Advance fully recovered on this certificate. | AED 504,000.00 | Owner | |
| 25 Sep 2025 | INV-001 | Bank transfer | Certificate 1: 480,000 certified, less 10% retention and 20% advance recovery. | AED 336,000.00 | Owner | |
| 20 Aug 2025 | Not against an invoice | Cheque | Advance against materials, not against any invoice. Recovered at 20% of each certificate. | AED 150,000.00 | Owner |