Villa — Nad Al Sheba

Guest (view only)

Plot 214, Nad Al Sheba 3, Dubai

This project is completed. It stays fully readable; an admin can reopen it from Handover.

Schedule

Start
17 Aug 2025
Target completion
17 Aug 2026
originally 30 Jun 2026
Milestones done
12 of 12
Delayed
10

Extended by seven weeks. Three: the Civil Defence resubmission after the basement sprinkler coverage was returned. Two: a six-week lead time on the imported marble, ordered late because the selection was reopened. Two: rectification of the north-elevation blockwork found at the structural inspection.

Programme

The full schedule document. Every revision is kept.

  • Rev CCurrent

    18 Aug 2026 · Contractor · Recovery programme agreed at the March delay meeting. Completion 17 August 2026.

  • Rev B

    18 Aug 2026 · Contractor · Reissued after the Civil Defence rejection moved the fit-out start by three weeks.

  • Rev A

    18 Aug 2026 · Contractor · Baseline programme issued at mobilisation, 46 weeks to 30 June 2026.

Milestones

  • Site mobilisationDone

    Planned 31 Aug 2025 · done 28 Aug 2025

  • Excavation & shoringDone8 days late

    Planned 30 Sep 2025 · done 08 Oct 2025

  • Raft foundation pouredDone

    Planned 05 Nov 2025 · done 05 Nov 2025

  • Superstructure to roof slabDone19 days late

    Planned 15 Jan 2026 · done 03 Feb 2026

  • Blockwork & plasterDone19 days late

    Planned 28 Feb 2026 · done 19 Mar 2026

  • MEP first fix completeDone22 days late

    Planned 31 Mar 2026 · done 22 Apr 2026

  • Waterproofing & screedDone16 days late

    Planned 20 Apr 2026 · done 06 May 2026

  • Joinery & marble installationDone34 days late

    Planned 25 May 2026 · done 28 Jun 2026

  • MEP second fix & commissioningDone34 days late

    Planned 10 Jun 2026 · done 14 Jul 2026

  • Snagging & de-snaggingDone47 days late

    Planned 20 Jun 2026 · done 06 Aug 2026

  • Practical completionDone41 days late

    Planned 30 Jun 2026 · done 10 Aug 2026

  • HandoverDone48 days late

    Planned 30 Jun 2026 · done 17 Aug 2026

Comments

  • Practical completion signed today. De-snagging closed out bar two cosmetic items. Handover on the 17th as agreed.

    Contractor · 10 Aug 2026

  • Agreed. Move it, and no claim from my side if there is none from yours.

    Owner · 30 Mar 2026

  • Honestly: it goes. Three weeks on Civil Defence, two on the marble lead time, two on the north-elevation blockwork rectification. Recommending we move the target to 17 August and reissue the programme as Rev C, rather than hold a date nobody believes.

    Consultant · 30 Mar 2026

  • I would rather know now than in June. What does this do to the June handover date, honestly?

    Owner · 18 Mar 2026

  • Revised layout is with the fire consultant today. We will resubmit by the 6th. Adding a second joinery crew from April to pull some of it back.

    Contractor · 17 Mar 2026

  • Civil Defence returned the fire submission yesterday: basement store sprinkler coverage missing from the drawings. Three weeks minimum before we are back in the queue. The fit-out start has no float left after this.

    Consultant · 17 Mar 2026

  • Noted, and agreed it is absorbed. Please keep the breaking-out records — if this comes up at final account we will want the dates.

    Consultant · 09 Oct 2025

  • Excavation finished eight days late — we hit rock at the north-east corner and had to break it out rather than dig. Absorbed within the float, the raft pour still holds for 5 November.

    Contractor · 09 Oct 2025