Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Schedule
The schedule could not be loaded — this is a setup problem, not an empty schedule. A required migration has not been applied; the exact cause is in the server log.
Extended by seven weeks. Three: the Civil Defence resubmission after the basement sprinkler coverage was returned. Two: a six-week lead time on the imported marble, ordered late because the selection was reopened. Two: rectification of the north-elevation blockwork found at the structural inspection.
Programme
The full schedule document. Every revision is kept.
- Rev CCurrent
18 Aug 2026 · Contractor · Recovery programme agreed at the March delay meeting. Completion 17 August 2026.
- Rev B
18 Aug 2026 · Contractor · Reissued after the Civil Defence rejection moved the fit-out start by three weeks.
- Rev A
18 Aug 2026 · Contractor · Baseline programme issued at mobilisation, 46 weeks to 30 June 2026.
Milestones
- Site mobilisationDone
Planned 31 Aug 2025 · done 28 Aug 2025
- Excavation & shoringDone8 days late
Planned 30 Sep 2025 · done 08 Oct 2025
- Raft foundation pouredDone
Planned 05 Nov 2025 · done 05 Nov 2025
- Superstructure to roof slabDone19 days late
Planned 15 Jan 2026 · done 03 Feb 2026
- Blockwork & plasterDone19 days late
Planned 28 Feb 2026 · done 19 Mar 2026
- MEP first fix completeDone22 days late
Planned 31 Mar 2026 · done 22 Apr 2026
- Waterproofing & screedDone16 days late
Planned 20 Apr 2026 · done 06 May 2026
- Joinery & marble installationDone34 days late
Planned 25 May 2026 · done 28 Jun 2026
- MEP second fix & commissioningDone34 days late
Planned 10 Jun 2026 · done 14 Jul 2026
- Snagging & de-snaggingDone47 days late
Planned 20 Jun 2026 · done 06 Aug 2026
- Practical completionDone41 days late
Planned 30 Jun 2026 · done 10 Aug 2026
- HandoverDone48 days late
Planned 30 Jun 2026 · done 17 Aug 2026
Comments
Practical completion signed today. De-snagging closed out bar two cosmetic items. Handover on the 17th as agreed.
Contractor · 10 Aug 2026
Agreed. Move it, and no claim from my side if there is none from yours.
Owner · 30 Mar 2026
Honestly: it goes. Three weeks on Civil Defence, two on the marble lead time, two on the north-elevation blockwork rectification. Recommending we move the target to 17 August and reissue the programme as Rev C, rather than hold a date nobody believes.
Consultant · 30 Mar 2026
I would rather know now than in June. What does this do to the June handover date, honestly?
Owner · 18 Mar 2026
Revised layout is with the fire consultant today. We will resubmit by the 6th. Adding a second joinery crew from April to pull some of it back.
Contractor · 17 Mar 2026
Civil Defence returned the fire submission yesterday: basement store sprinkler coverage missing from the drawings. Three weeks minimum before we are back in the queue. The fit-out start has no float left after this.
Consultant · 17 Mar 2026
Noted, and agreed it is absorbed. Please keep the breaking-out records — if this comes up at final account we will want the dates.
Consultant · 09 Oct 2025
Excavation finished eight days late — we hit rock at the north-east corner and had to break it out rather than dig. Absorbed within the float, the raft pour still holds for 5 November.
Contractor · 09 Oct 2025