Villa — Nad Al Sheba
Guest (view only)Plot 214, Nad Al Sheba 3, Dubai
This project is completed. It stays fully readable; an admin can reopen it from Handover.
Basement — Additional Tanking to Retaining Wall
Variation
This page could not check who holds the decision on this item, so the decision panel is hidden. This is a setup problem, not a permissions one — public.can_approve() is unavailable.
Original submission
Contractor · Oct 27, 2025, 05:15 AMCost: AED 64,000.00
Ground investigation found a higher water table on the north boundary. Additional bituminous tanking and a drainage board to the retaining wall. Two weeks, absorbed within the float.
- Tanking-Variation-Quotation.pdf3.0 KB
- ApprovedConsultant · Nov 3, 2025, 07:00 AM
Agreed. Proceed, and reflect the cost in the next application.