2 waiting for an answer. Anyone on the project can answer.

  • Does anyone know when DEWA are energising the substation? The temporary supply is fine for now but the lift commissioning needs permanent power.

    Contractor · asked 17 days ago · Anyone can answer

    • I chased them on Tuesday. They said within two weeks, no firm date. I will push again.

      Owner

  • Before we close the basement ceiling — is the sprinkler layout on SD-610 Rev B final, or is the civil defence comment still outstanding?

    Contractor · asked 17 days ago · Asked of Consultant

    About drawing: SD-610 — Sprinkler Coverage, Basement Rev B
Answered (4)
  • Is the grout on the majlis threshold going to be redone in one go, or patched? I would rather it was all lifted than see a join.

    Owner · asked 17 days ago · Anyone can answer

    Answered
    About snag: #3 Grout colour inconsistent across the threshold (Majlis / entrance threshold)
    • All of it, in one pour. Patching a threshold never matches — it will be lifted back to the door line.

      Contractorthe answer

  • Which extract fan was actually installed in the guest WC? The snag says undersized and I want to check it against the schedule before you order a replacement.

    Consultant · asked 17 days ago · Anyone can answer

    Answered
    About snag: #2 Extract fan noisy and undersized (Guest WC, ground floor)
    • It is a 100mm inline, 85 m³/h. The schedule calls for 150 m³/h so it is genuinely undersized — replacement is on order, arriving Sunday.

      Contractorthe answer

  • The elevations show the majlis window in dark bronze. Is that the same finish as the entrance screen, or a shade lighter?

    Owner · asked 17 days ago · Anyone can answer

    Answered
    About drawing: EL-201 — North & East Elevations Rev A
    • Same finish — both are RAL 8019 fine texture. The supplier quoted them as one batch so they will match.

      Contractorthe answer

    • Confirmed. It is the same system throughout the front elevation.

      Consultant

  • Rev B moved the kitchen island 300mm north. Does the floor waste move with it, or stay where SD-310 shows it?

    Contractor · asked 17 days ago · Anyone can answer

    Answered
    • The waste stays. The island overhangs it by design — see the note on SD-310 Rev B, bottom right.